Roanoke Times Copyright (c) 1995, Landmark Communications, Inc. DATE: THURSDAY, May 24, 1990 TAG: 9005240074 SECTION: VIRGINIA PAGE: B-4 EDITION: METRO SOURCE: DATELINE: SURRY LENGTH: Short
Virginia Power spokesman Carl Baab said the shutdowns took place shortly after noon Tuesday when a faulty fire-protection system activated and sprayed water on a transformer outside the Unit 1 reactor building. Control-room operators almost immediately shut down Unit 2 after the automatic shutdown of Unit 1.
The Unit 1 reactor may be restarted by late today, and the Unit 2 reactor may be brought on-line within two or three days, Baab said.
- Associated Press
by CNB