5-YEAR PLAN SUGGESTED IN PULASKI WATER-SYSTEM STUDY

The five-year, $1.3 million water improvement plan to be recommended next month to Pulaski Town Council is as follows:\

1993-1994

Mashburn Avenue connection to Peppers Ferry Road: $15,000.

Work on four pump stations: $36,000.

Computer model of water system: $18,000.

Trench box: $1,600.\

1994-95

Approved disposal site for alum sludge: $5,000.

Clean sludge pond: $30,000.

Fourth Street Southeast, Washington to Pierce Avenue: $43,150.

Pearce Place: $15,000.

Peppers Ferry Road, Twin Oaks to Beth Scott area: $30,000.

Peakland subdivision, Newbern Road $40,000.

Relocate raw water intake, permanent air jets: $12,000.

Buy service truck: $19,000 Leak detector: $4,000.

Work on three pump stations: $21,000.

Replace Madison Avenue pump station: $50,000.\

1995-96

Virginia 611 (Bob White Boulevard): $121,050.

Buy vehicle: $10,000.

Repairs to Gatewood Dam: $150,000.

Paint two water tanks: $30,000.\

1996-97

U.S. 11 tank to Pleasant Hill: $139,025.

Buy vehicle: $10,000.

Improvements to Hogan's Dam: $400,000.\

1997-98

Franklin Avenue, Fourth to Main Street: $15,450.

First Street Northeast, Duncan to Washington Avenue: $41,700.

Stuart/Elm Street, Graham to Jackson Street: $34,000.

Tie in four large lines to improve efficiency: $224,000.



 by CNB